Ngā ara ki te whakaoranga

Road to recovery

In 2023, our local roading network was severely impacted by Cyclones Hale and Gabrielle. Almost all rural roads were closed, leaving communities cut off for weeks. The damage was extensive with 8 bridges destroyed, 54 bridges sustained major damage and there were numerous slips and dropouts affecting key routes. The scale of destruction has left a recovery bill stretching into the hundreds of millions of dollars.

The total cost to restore our local roading network to its pre-cyclone condition has been assessed at $465 million. But to build back stronger and more resilient, we need $725 million. So far, we've received $245 million in funding, with an additional $85 million for the initial emergency response costs.

Our focus remains clear - to reopen roads for isolated residents, restore access for heavy freight to support our rural communities and prioritise school bus routes, safe community connections, and forestry and farm access - especially where animal welfare is at risk.

The funding of projects


- $76.7m on destroyed bridges - fixing 4 bridges with the government funding.
- $23m on  65 damaged bridges.
- $1m on minor repairs to 35 bridges
- $45m Tiniroto Road - investigation and construction of bypass across the Hangaroa River before the first bluff and back over the river after bluff 2.
- $51.8m to fix major slips and dropouts
- $36m working in partnership with iwi on projects to provide greater resilience to communities

On this page

Bridge repairs or replacement

We assessed all 424 bridges in our region following Cyclone Gabrielle:

  • 6 bridges were destroyed
  • 65 bridges required major repairs
  • 35 required minor repairs to ensure their resilience in future severe weather events.
  • 32 bridges were also damaged in severe weather events prior to, or post Cyclone Gabrielle

Tiniroto Road - Hangaroa Bluffs

Tiniroto Road at the Hangaroa Bluffs sustained major damage at the bluffs following Cyclone Gabrielle. Around 1.4km of road was undermined, with river protection works either partially or completely destroyed. The 2 lane road was scoured away, leaving less than one lane in some sections. Repairs included rebuilding retaining wall structures and restoring rock protection. The road was initially reopened to single-lane access.

However, recurring weather events continued to destabilise the area, causing further scouring and rockfall risk. In June 2023, the road was closed due to the danger of falling rocks. After 10 months of extensive repair and stabilisation work, the road reopened.

Tiniroto Bluffs reports

In October 2024, following detailed engineering investigations and with $45M in government funding, a long-term solution was confirmed: a bypass was identified as the most suitable and resilient solution for the area.

Slips and dropouts

As part of Phase 4 of the recovery programme, $51.8m  has been allocated to repair slips and dropouts that met the funding criteria. This is jointly funded by $40.5 million from NZTA and $11.3 million from the government.

Progress to date
  • Phases 1 and 2: 19 sites - works completed in 2023
  • Phase 3: 43 sites  - works completed in 2023
  • Phase 4: 343 sites - works began October 2024
    - 246 sites completed by July 2025
Site selection criteria

Slips and dropout were prioritised based on:

  • Current impact on the level of service
  • Regional economic importance of the route

Roadside drainage - supporting iwi communities

A $36.3 million, this phased programme is underway to improve the resilience of alternative routes identified by iwi and community stakeholders. These routes are vital for emergency access, cultural connection, and everyday travel.

Phase 1: 132 sites - work scheduled January - June 2025

Focus - remediating surface and drainage issues of roads that serve as emergency alternatives when state highways are closed.

Phase 2: 150 sites - work scheduled September - December 2026

Focus - roads that are the sole access to remote or vulnerable communities, including sites of cultural significance.
Prioristed in partnership with iwi.

Site selection criteria

Sites and routes were prioristed by iwi using the following criteria:

  • current impact on level of service
  • cultural importance of the location or destination
  • regional economic importance of the route
  • evacuation restrictions in case of emergency
  • school bus route access

Waihau Road

In the June 2023, a significant landslide washed out part of Waihau Road, approx 4.8km from the intersection with SH35. Geotechnical engineers inspected the site, where 5m of the road had been lost, and confirmed it was part of a much larger 110m fault.

The dropout was caused by a landslide and debris flow originating more than 30m above the road. The debris overwhelmed the road, blocked drainage systems and led to flooding what washed out the road surface. For a time, residents only had walking access around the slip.

Repair and reopening timeline
  • November 2023: road access reinstated for residents.
  • December 2023: road reopened to all traffic following a favourable risk assessment.
  • No stopping signs installed at both ends of the repaired section of road.
Ongoing risk management

Due to the potential for the landslide to reactivate, the following weather-triggered alerts are in place.

MetService warning levels - that include this area:
  • Orange Warning - residents and campers must closely monitor forecast and be prepared to evacuate.
  • Red Warning - the road will close; residents and campers must evacuate.

These measures are in place to protect public safety.

Waihau Road slip reports

7 December 2023 - Post-Slip Risk Assessment Report
27 July 2023 - Updated report - LDE Report on Waihau Road Slip

Tauwhareparae Road

Tauwhareparae Road has sustained significant damage, including:

  • 4 damaged bridges
  • major slips
  • 2 landslides at the 17 and 26km marks

Staff are preparing a full business case to apply for funding to restore the road. This process may take some time and will include options for alternative routes to improve long-term resilience and access.

Landslide dam update - 28 August

A landslide dam on Tauwhareparae Road has been assessed as low to minimal risk of failure.  Key details:

  • size - approximately 1.2 hectares
  • water volume - estimated at 26,000m3
  • dimensions - roughly 5m deep and 20m wide
  • flow - water is freely flowing through the dam, reducing pressure and risk
  • gradient - the dam has a low slope, which further lowers the chance of rapid failure.

The dam of water is being actively monitored and inspected, especially following rainfall, to ensure public safety and early detection of any changes.

Road closure information

For up to date information on closed roads, restrictions and bridges closed

Damage