The footbridge that links Grundy Street and Oak Street will be unavailable for another week.

The footbridge was temporarily removed at the beginning of the month for repairs. The bridge is being painted and the deck on the bridge replaced. This work was estimated to take 2 weeks but corrosion has been found on the girder ends. These are now being removed and repaired which will take another 2 week.

The footbridge is now due to open on Friday 26 November.

The footbridge is used extensively by cyclists and pedestrians to link up with the footbridge between Oak Street and Aberdeen Road. While the repairs are being carried out access is via Stout Street

We apologise for any inconvenience this may cause users.